Prior Approval London 2025: Complete Guide

When you need prior approval, how to apply, and what the council considers. A middle ground between permitted development and full planning permission.

Key Facts

  • Application fee: £120 for householder prior approval
  • Decision time: 56 days (automatic approval if no response)
  • Common use: Larger rear extensions (6-8m single storey)
  • Neighbour notice: Council must notify adjoining neighbours

Prior approval is a streamlined planning process for specific types of development that are technically "permitted development" but require council notification. The council can only consider limited matters—typically neighbour impact, transport, or flooding—not the broader planning merits.

When Prior Approval Is Required

Larger Home Extensions

Single storey rear extensions between 4-8m (detached) or 3-6m (other houses). This extends standard PD limits but requires neighbour notification.

Office to Residential (Class MA)

Converting offices to homes. Council considers transport, flooding, contamination, and impact on provision of office space.

Agricultural Buildings

Converting agricultural buildings to residential. Siting, design, transport, flooding, contamination, and noise considered.

Telecommunications

Mobile phone masts and equipment. Siting and appearance are the main considerations.

Larger Home Extension Rules

The most common householder use of prior approval is for larger single storey rear extensions that exceed standard permitted development limits.

House TypeStandard PDWith Prior Approval
Detached houseUp to 4mUp to 8m
Semi-detachedUp to 3mUp to 6m
Terraced houseUp to 3mUp to 6m

Note: Maximum height 4m, eaves 3m. Must be single storey only. Does not apply in conservation areas, AONB, or to listed buildings.

The Prior Approval Process

1

Submit Application

Complete form, pay £120 fee, provide site plan and elevations showing proposed extension.

2

Neighbour Notification

Council writes to adjoining neighbours giving 21 days to comment on impact.

3

Council Assessment

Council can only consider impact on amenity of adjoining properties—not design, materials, or planning policy.

4

Decision (56 Days)

Three outcomes: prior approval granted, prior approval refused, or prior approval not required. No response = deemed approval.

What Council Can and Cannot Consider

Can Consider

  • Impact on adjoining neighbours' amenity
  • Loss of light to neighbours
  • Overbearing impact
  • Overlooking (if relevant)

Cannot Consider

  • Design quality or materials
  • Whether it suits the area
  • Planning policy preferences
  • Impact on your own amenity

Frequently Asked Questions

Can neighbours stop my extension?

Only if their objection relates to impact on their amenity and the council agrees the impact is significant. General objections about not liking the development are not valid grounds for refusal.

What if the council doesn't respond?

After 56 days without a decision, prior approval is deemed granted. You can proceed with development, though it's wise to get written confirmation.

Can I appeal a refusal?

Yes, you can appeal to the Planning Inspectorate. Appeals are free and typically decided within 8-12 weeks for householder applications.